Planning appeal decision
Dismissed30 August 20233322179
Land at Winter Lane, LA8 9JA
- Authority
- Westmorland and Furness Council
- Appeal type
- other · Community Infrastructure Levy Appeal
- Procedure
- Written Representations
- Development
- Not Applicable
- Inspector
- McEntee K
Main issues, as the Inspector framed them
- Whether the alleged breaches (failure to submit a Commencement Notice before starting works and failure to pay CIL within 30 days) occurred
What decided it
The appellant admitted the factual breach of failing to submit a Commencement Notice before commencing works, which triggered full CIL liability and the subsequent late payment surcharge.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®