Allowed14 October 20253364658

OS Fields 7456 And 6163, Amplecarr, Husthwaite, North Yorkshire, YO61 4QA

Installation of solar photovoltaic (PV) array/solar farm with associated infrastructure

Authority
North Yorkshire Council
Appeal type
major · Planning Appeal
Procedure
Hearing
Development
utilities-energy · Other Major Developments
Inspector
Brooker M

Main issues, as the Inspector framed them

  • The effect of the proposed development on Best and Most Versatile agricultural land.
  • The effect of the appeal scheme on the Landscape, including the Howardian Hills National Landscape.

What decided it

The substantial weight given to the scheme's economic, social and environmental benefits outweighed the significant harm to BMV agricultural land and the moderate/minor landscape harms.

the substantial benefits of the renewable energy scheme outweighed the significant harm from loss of BMV agricultural land and the minor/moderate adverse landscape impacts

Framework references: 187

Plan policies cited: Policy RM6, Policy S5, Policy E7, Policy E6

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.

In the app this decision sits on the map beside every other appeal around it, with the full reasoning summary, the letter held on file, and the case law it applies.