Planning appeal decision
180 Queensbridge Road, Hackney, London, E8 4QE
Planning appeal 3256218 at 180 Queensbridge Road, Hackney, London, E8 4QE (London Borough of Hackney) was decided (quashed on legal grounds) on 15 June 2021 by Inspector Lewis D, by written representations. The main issue, as the Inspector framed it: Whether the enforcement notice specifies with sufficient clarity the alleged breach of planning control and the steps required for compliance.
Without planning permission, the erection of a side roof extension
- Authority
- London Borough of Hackney
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Householder developments
- Inspector
- Lewis D
- Postcode
- E8 4QE
Main issues, as the Inspector framed them
- Whether the enforcement notice specifies with sufficient clarity the alleged breach of planning control and the steps required for compliance
What decided it
The enforcement notice failed the Miller-Mead test by not specifying with sufficient clarity what breach of planning control was alleged and what steps were required to remedy it, and the defect could not be corrected without causing injustice to either party.
The decision letter
Town Planner Pro holds this letter. The Appeals plan opens it and every other letter we hold, all of them searchable, with the main issues and what decided each case picked out. We do not show letters on the free site because they carry people’s names and addresses.
With an account
What an account adds to this decision


More decisions in London Borough of Hackney
The authority’s record since 2016 · every decision in 2021
- Notice upheld23 September 20263368635Flat 6, Brooks Lodge, 194A Hoxton Street, London, N1 5HU
- Notice varied and upheld18 September 202633607242B Woodberry Down, Hackney, London, N4 2TG
- Dismissed14 May 20266003534212 Millfields Road, London, E5 0AR
- Notice upheld27 March 2026333760072 Powerscroft Road, Hackney, London, E5 0PP
- Notice upheld27 March 2026333759974 Powerscroft Road, Hackney, London, E5 0PP
The main issues, what decided it, the planning balance and the policies and judgments listed as cited are read from the published letter by Town Planner Pro and are our summary, not the Inspector’s words; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®