Dismissed4 October 20213274190

Blenheim Power, 56 Blenheim Road, Lancing Business Park, Lancing, BN15 8UQ

An Urban Reserve Flexible Energy Facility and associated equipment

Authority
Adur District Council
Appeal type
minor · Planning Appeal
Procedure
Written Representations
Development
utilities-energy · Minor general industry/storage/warehousing
Inspector
Reid J

Main issues, as the Inspector framed them

  • whether the proposed development would be an acceptable use of resources in the context of relevant Development Plan policies
  • whether the proposed development would be an acceptable re-use of employment land

What decided it

The proposed development would be contrary to the Development Plan when taken as a whole, relying on fossil fuels in conflict with local climate commitments and causing harmful loss of employment land without demonstrated necessity at the site.

The conflict with the Development Plan was not outweighed by other considerations including the Framework.

Framework references: 7, 152, 154

Plan policies cited: Policy 1, Policy 19, Policy 25

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.

In the app this decision sits on the map beside every other appeal around it, with the full reasoning summary, the letter held on file, and the case law it applies.