Town Planner Pro
Search appeal decisions

Planning appeal decision

Notice upheld14 February 20223283119

5 Lamb Bank, MALVERN, WR14 4NE

The erection of an extension

Authority
Malvern Hills District Council
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
other · Householder developments
Inspector
Symons G

What decided it

Four calendar months is a reasonable compliance period for removal of the extension, and the appellant has the option to seek relaxation of the notice through pre-planning enquiry if an alternative scheme is found acceptable.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.

In the app this decision sits on the map beside every other appeal around it, with the full reasoning summary, the letter held on file, and the case law it applies.