Planning appeal decision
Notice varied and upheld23 November 20223292643
Horsley Banks Farm, Horsley, NEWCASTLE UPON TYNE, NE15 0NS
Without planning permission, the construction of a stable
- Authority
- Northumberland County Council
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Hearing
- Development
- other · Other Major Developments
Main issues, as the Inspector framed them
- The issue is whether the compliance period is reasonable.
What decided it
The Inspector concluded that the original compliance periods were too short and that nine months was a reasonable period, a variation unopposed by the Council.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®