Planning appeal decision
Chy Vounder, Trenance, Mawgan Porth, NEWQUAY, Cornwall , TR8 4BT
the construction of a detached dwellinghouse and the provision of a new vehicular access (all other matters reserved)
- Authority
- Cornwall Council
- Appeal type
- minor · Planning Appeal
- Procedure
- Written Representations
- Development
- residential · Minor Dwellings
- Inspector
- Andrews M
Main issues, as the Inspector framed them
- Whether the principle of a new dwelling on the site is acceptable having regard firstly to the site's location as regards local and national planning policy and secondly to the effect of the development on the character and appearance of the area
What decided it
The Council's initial pre-application advice and officer's report exercising reasonable interpretation of policy, combined with the site's characteristics as established residential garden land within the settlement boundary, outweighed the subsequent Member refusal and Parish Council objections.
Framework references: 174
Plan policies cited: Policy 2, Policy 3, Policy 7, Policy 12, Policy 23, Policy 21c
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®