Planning appeal decision
Land West of New Works Lane, Telford, Shropshire, TF6 5BS
the installation of a Solar Farm and associated infrastructure. Summary of Recommendation: That the appeal be dismissed. Procedural and
- Authority
- Telford and Wrekin Council
- Appeal type
- major · Planning Appeal
- Procedure
- Inquiry
- Development
- utilities-energy · Other Major Developments
- Inspector
- Robins M
Main issues, as the Inspector framed them
- the effect of the proposal on the landscape character and appearance of the area, including that of the Shropshire Hills Area of Outstanding Natural Beauty (AONB), including the effect on recreational users
- whether the proposal would conflict with the development plan and if so whether there are any material considerations that would outweigh that conflict; the planning balance
What decided it
The Secretary of State's disagreement with the Inspector's finding that landscape harm was significant/unacceptable, instead finding it did not amount to a significant adverse effect under Policy ER1, tipping the balance in favour of the substantial renewable energy and other benefits.
the significant weight given to renewable energy production, significant weight given to planting/community benefits, and limited weight given to economic benefits outweighed the significant weight attributed to landscape harm and very limited harm to the AONB setting
Framework references: 174, 176, 155, 158, 152, 56, 57
Plan policies cited: Policy ER 1, Policy NE 7, Policy BE 1, Policy NE 1, Policy P1, Policy WF1
Judgments cited: DLA Delivery Limited v Baroness Cumberlege of Newick [2018] EWCA Civ 1305
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®