Planning appeal decision
New Mill Farm, Thormanby, York, YO61 4NN
construction of an anaerobic digestion and combined heat and power facility without complying with conditions attached to planning permission Ref 14/01736/FUL, dated 12 November 2014
- Authority
- Hambleton District Council *
- Appeal type
- minor · Planning Appeal
- Procedure
- Written Representations
- Development
- utilities-energy · Change of use
- Inspector
- Wilkinson F
Main issues, as the Inspector framed them
- The effect that removing the conditions would have on the development strategy for the area
What decided it
The support given by the National Planning Policy Framework and Local Plan Policy RM6 to renewable energy proposals, combined with the modest traffic impacts and absence of material harm to living conditions, outweighed the Council's concern about loss of control over the nature of the operation.
Framework references: 158, 111
Plan policies cited: Policy RM6, Policy IC2, Policy EG7, Policy S5, Policy E2