Planning appeal decision

Notice varied and upheld6 February 20233301292

Orrell Hill Farm , Orrell Hill Lane, Ince Blundell, L38 5DA

without planning permission and within the last ten years, the unauthorised change of use of the land from agricultural to storage of buses, caravans and other non-agricultural vehicles

Authority
Sefton Metropolitan Borough Council
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
other · Change of use
Inspector
Moore D

Main issues, as the Inspector framed them

  • Whether the material change of use to storage of buses, caravans and other non-agricultural vehicles occurred ten or more years prior to the enforcement notice such that it is too late for the Council to take action
  • Whether the three month compliance period is reasonable

What decided it

The appellant's evidence failed to establish on the balance of probabilities that the unauthorised use had continued for ten or more years without interruption, but the three-month compliance period was found to be unreasonably short and was extended to six months.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.