Notice upheld27 November 20233323189

The Mistle, Firth House Barn, Halifax, HX4 0EL

Without planning permission, the construction of a detached stone building on the Land comprised of a garage with annexe joined to the north side of the building on ground floor level and office on the first floor (in the approximate position indicated on the attached plan marked Plan ENF1 and as seen in the digital photographs attached to this Notice at Appendix 3)

Authority
Calderdale Metropolitan Borough Council
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
other · Other minor developments
Inspector
Wraight G

Main issues, as the Inspector framed them

  • Whether the period for compliance specified in the enforcement notice (three months) falls short of what should reasonably be allowed

What decided it

The limited evidence of contractor non-availability and the appellant's substantial prior opportunity to arrange demolition meant the three-month compliance period was reasonable.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.