Planning appeal decision
122 Minories & 14 Crosswall, EC3N 1NT
Planning appeal 3324906 at 122 Minories & 14 Crosswall, EC3N 1NT (City of London Council) was allowed on 27 September 2023 by Inspector McEntee K, by written representations. The main issue, as the Inspector framed it: Whether the Collecting Authority failed to serve a Liability Notice in respect of the development to which the surcharge relates, as required by Regulation 65(1) of the Community Infrastructure Levy Regulations 2010.
- Authority
- City of London Council
- Appeal type
- other · Community Infrastructure Levy Appeal
- Procedure
- Written Representations
- Development
- other · Not Applicable
- Inspector
- McEntee K
Main issues, as the Inspector framed them
- Whether the Collecting Authority failed to serve a Liability Notice in respect of the development to which the surcharge relates, as required by Regulation 65(1) of the Community Infrastructure Levy Regulations 2010
What decided it
The Council's failure to serve the Liability Notice within a reasonable timeframe (8 months after planning permission) breached Regulation 65(1) and effectively prevented the appellant from submitting a valid Commencement Notice and paying CIL on time.
The decision letter
Town Planner Pro holds this letter. The Appeals plan opens it and every other letter we hold, all of them searchable, with the main issues and what decided each case picked out. We do not show letters on the free site because they carry people’s names and addresses.
With an account
What an account adds to this decision


More decisions in City of London Council
The authority’s record since 2016 · every decision in 2023
- Dismissed4 August 2026600657973 Aldgate High Street, London, EC3N 1BD
- Dismissed21 January 20263364494102 Cheapside, London, EC2V 6DT
- Dismissed21 January 20263364492102 Cheapside, London, EC2V 6DT
- Allowed24 December 2025337395290 Liverpool Street, London, EC2M 2AT
- Allowed29 October 202533534791 Portsoken Pavilion , Aldgate Square, London, City Of London, EC3N 1AF
The main issues, what decided it, the planning balance and the policies and judgments listed as cited are read from the published letter by Town Planner Pro and are our summary, not the Inspector’s words; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®