Planning appeal decision
The Creamery , Trevarrian, Newquay , TR8 4AH
redevelopment of site for mixed use scheme
- Authority
- Cornwall Council
- Appeal type
- major · Planning Appeal
- Procedure
- Written Representations
- Development
- residential · Other Major Developments
- Inspector
- Harrington S
Main issues, as the Inspector framed them
- whether the proposal would make adequate provision for business space, having regard to supporting economic growth and the requirements of the development plan
- the effect of the proposal on the character and appearance of the area
- whether the proposal secures adequate provision for any additional need for education, public open space and health provision arising from the development, and mitigation measures relating to the Penhale Dunes Special Area of Conservation (SAC)
What decided it
The failure to adequately demonstrate that the proposal would make adequate provision for business space having regard to supporting economic growth and the requirements of LP Policy 5, which was given significant weight and outweighed the moderate benefits of housing provision and other benefits.
The significant weight given to the conflict with LP Policy 5 on business space provision outweighed the moderate weight afforded to housing supply on previously developed land and the limited benefits of public open space, biodiversity net gain, commercial uses and construction industry support, resulting in dismissal.
Plan policies cited: LP Policy 5, LP Policy 2, LP Policy 12, LP Policy 21, LP Policy 23, saved Policy 14 of the Restormel Borough Local Plan (RBLP), LP Policy 28, LP Policy 22, LP Policy 8, LP Policy 27
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®