Planning appeal decision
Notice varied and upheld24 April 20243329177
3 Robartes Terrace, LOSTWITHIEL, PL22 0AR
without planning permission, the construction of a garage
- Authority
- Cornwall Council
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Householder developments
- Inspector
- Wilson S
Main issues, as the Inspector framed them
- Whether the steps required by the enforcement notice are excessive (ground f)
- Whether the period for compliance is reasonable (ground g)
What decided it
The period for compliance was unreasonable at six months given the significant nature of the demolition task and the appellants' circumstances, justifying variation to nine months.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®