Planning appeal decision
land south west of the homestead, penzance, TR20 8UJ
Without planning permission, the construction of a building comprising of a caravan and wooden extension used for residential purposes, the erection of a polytunnel and the associated material change of use of the land from agricultural to a mixed use comprising of agricultural and residential. The approximate position of the residential building is indicated by a blue ‘X’ on the attached plan”
- Authority
- Cornwall Council
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- residential · Change of use
- Inspector
- McEntee K
Main issues, as the Inspector framed them
- Whether the compliance period of 16 months is reasonable and proportionate
What decided it
The compliance period of 16 months, when combined with the 6 months already elapsed since appeal submission, provides a total of approximately 22 months which the Inspector considered reasonable and proportionate to address the appellants' relocation needs while remedying the harm to the countryside.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®