Planning appeal decision
West Quarry, Appley Lane North, Appley Bridge, WN6 9EA
without planning permission, the undertaking of engineering operations on the Land, consisting of:
- Authority
- West Lancashire District Council
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- minerals-waste · Other Major Developments
- Inspector
- Walker A
Main issues, as the Inspector framed them
- Whether the alleged breach of planning control has occurred as a matter of fact (ground b)
- Whether the matters alleged in the notice constitute a breach of planning control (ground c)
- Whether the steps required by the notice exceed what is necessary to remedy the breach of planning control (ground f)
What decided it
The engineering operations and tree clearance were carried out as a single development operation without planning permission, constituting a breach of planning control that the enforcement notice reasonably requires to be remedied.
Plan policies cited: 08/80/1151/6
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®