Planning appeal decision
Quashed On Legal Grounds26 May 20263349151
81 Imperial Drive, HARROW, HA2 7DU
the construction of an outbuilding in the rear garden
- Authority
- London Borough of Harrow
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Householder developments
- Inspector
- Ghafoor A
Main issues, as the Inspector framed them
- Whether the alleged construction of an outbuilding constitutes a breach of planning control
- Whether it is too late to take enforcement action
What decided it
The extended outbuilding was substantially completed by April 2020, placing the breach beyond the four-year enforcement period, making enforcement action time-barred under section 174 of the Town and Country Planning Act 1990.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®