Planning appeal decision
Dismissed11 November 20243349318
72 -80 Akeman Street, BUILDING BLOCK A - ROOFTOP, TRING, HP23 6AF
- Authority
- Dacorum Borough Council
- Appeal type
- other · Community Infrastructure Levy Appeal
- Procedure
- Written Representations
- Development
- residential · Not Applicable
- Inspector
- Ghafoor A
Main issues, as the Inspector framed them
- Whether the breach which led to the imposition of surcharges for failure to submit a commencement notice and late payment occurred
- Whether the surcharges have been calculated correctly
What decided it
The CIL amount remained unpaid until September 2024, after the deemed commencement date of 23 March 2023, and the surcharges for late payment were correctly calculated under CIL Regulations 85.