Planning appeal decision

Allowed15 January 20253350191

Land West of Church Lane, Welby, Lincolnshire, NG32 3LS

the Installation of a solar farm comprising ground mounted solar photovoltaic panels, including mounting systems, inverters, underground cabling, stock proof fencing, CCTV, internal access tracks, electrical substation and associated infrastructure for a temporary period of 40 years

Authority
South Kesteven District Council
Appeal type
major · Planning Appeal
Procedure
Written Representations
Development
utilities-energy · Other Major Developments
Inspector
Plenty B

Main issues, as the Inspector framed them

  • The effect of the proposed solar farm on, and the potential loss of, agricultural land

What decided it

The substantial benefits of renewable energy generation and biodiversity net gain, combined with the temporary and reversible nature of the agricultural land loss and the site's constrained location relative to grid connection requirements, outweighed the moderate conflict with development plan policies on BMV agricultural land.

Framework references: 187, 192

Plan policies cited: Policy SP1, Policy RE1, Appendix 3 Criterion 9, Policy EN1, Policy EN6

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.

In the app this decision sits on the map beside every other appeal around it, with the full reasoning summary, the letter held on file, and the case law it applies.