Planning appeal decision

Dismissed23 May 20253355105

3 Westmeston Avenue, Saltdean, BRIGHTON, BN2 8AL

Authority
Brighton and Hove City Council
Appeal type
other · Community Infrastructure Levy Appeal
Procedure
Written Representations
Development
other · Not Applicable
Inspector
McEntee K

Main issues, as the Inspector framed them

  • Whether the alleged breach of failing to submit a Commencement Notice before starting works occurred
  • Whether the surcharge has been calculated incorrectly

What decided it

The appellant's failure to notify the Council before commencing demolition works meant a valid Commencement Notice could not be submitted before works began, constituting the breach that triggered the surcharge.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.

In the app this decision sits on the map beside every other appeal around it, with the full reasoning summary, the letter held on file, and the case law it applies.