Planning appeal decision

Allowed26 June 20253355855

23 – 25 HAYMARKET SHEFFIELD, S1 2AW

Authority
Sheffield City Council
Appeal type
other · Community Infrastructure Levy Appeal
Procedure
Written Representations
Development
other · Not Applicable
Inspector
McEntee K

Main issues, as the Inspector framed them

  • Whether the Council served a Liability Notice as soon as practicable after the planning permission
  • Whether the alleged breaches of Community Infrastructure Levy regulations occurred
  • Whether the Council issued a Demand Notice with an incorrectly determined deemed commencement date

What decided it

The Council's failure to serve a timely Liability Notice deprived the appellant of the opportunity to submit the necessary forms and thus prevented liability for the surcharges.