Notice upheld10 July 20253361451

Concrete Batching Plant, Creegbrawse, St Day, Redruth Cornwall, TR16 5QF

Without planning permission, the material change of land from nil use to a mixed use comprising of agricultural use (polytunnel approved under PA21/07698) and residential use, through the siting of a caravan for residential purposes (currently unoccupied) and associated development consisting of the connecting to residential services and construction of a concrete plinth and timer access steps”

Authority
Cornwall Council
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
caravan-gypsy · Change of use

Main issues, as the Inspector framed them

  • Whether the compliance period of 6 months should be extended to 12 months due to the appellant's serious health issues

What decided it

The 6-month compliance period, combined with the time already elapsed, provides a reasonable and proportionate timeframe for the appellant to arrange for the works to be carried out, and there is no justification for extension despite the appellant's health difficulties.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.

In the app this decision sits on the map beside every other appeal around it, with the full reasoning summary, the letter held on file, and the case law it applies.