Planning appeal decision
2A Red Lion Street, BOSTON, PE21 6NY
Without planning permission, the installation of two uPVC windows in the front elevation of the property
- Authority
- Boston Borough Council
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Other minor developments
Main issues, as the Inspector framed them
- Whether the compliance period of 6 months from the date the notice takes effect is reasonable and proportionate
What decided it
The compliance period of 6 months, when combined with the 4 months already elapsed during the appeal process, provides the appellant with approximately 10 months to arrange the necessary works, which the Inspector considered reasonable and proportionate.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®