Dismissed10 November 20213277408

1 Reynolds Wharf, Coalport, TELFORD, TF8 7HU

follows: Re-surfacing of the private access road serving the Reynolds Wharf residential development. The current surface is 100mm thick tarmacadam with a 5-10mm thick bitumen bonded aggregate finish which has worn significantly in the short time since the development was completed in c.2005. The plan is to plane off the existing finish and resurface the road surface with black tarmac to match the main road into the development. The block paved crossing points will remain unchanged. The cost of these works will be significant and will be borne by the residents. This proposal provides a hard wearing, cost effective finish which will be more sustainable than the original finish

Authority
Telford and Wrekin Council
Appeal type
major · Planning Appeal
Procedure
Written Representations
Development
utilities-energy · Other Major Developments
Inspector
Williamson J

Main issues, as the Inspector framed them

  • the effect of the proposal on the Ironbridge Gorge World Heritage Site (IGWHS)
  • whether the proposal would preserve or enhance the character or appearance of the Severn Gorge Conservation Area (SGCA)
  • whether the proposal would preserve the setting of adjacent Listed Buildings, namely the Grade II* former Coalport Chinaworks and the Grade II premises formerly occupied by the Nunway Manufacturing Company Limited

What decided it

The use of black tarmacadam would detract from the industrial origins of the area and harm the character and appearance of the heritage assets, outweighing the private economic benefits to residents.

The less than substantial harm to the character and appearance of the World Heritage Site, Conservation Area and listed building settings was not outweighed by the private economic benefits to residents, as no public benefits were identified.

Framework references: 184, 199, 202

Plan policies cited: Policy BE1, Policy BE3, Policy BE4, Policy BE5

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.