Planning appeal decision
40 Park Road, Stapleton, BRISTOL, BS16 1AT
the erection of a structure comprising of an elevated platform and scaffold supports projecting over the land and serving as additional amenity space for the abutting residential property
- Authority
- Bristol City Council
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Householder developments
- Inspector
- Hawkins S
Main issues, as the Inspector framed them
- Whether the requirements of the enforcement notice are excessive (ground f)
- Whether the time for complying with the requirements of the notice falls short of what should reasonably be allowed (ground g)
What decided it
A four-month compliance period was determined to be reasonable, balancing the need to remedy the breach promptly with the practical constraints of dismantling the structure, including contractor availability and seasonal weather conditions.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®