Planning appeal decision
Dismissed25 May 20233316747
Swampton Bungalow, The Rank, St Mary Bourne, SP11 6EN
- Authority
- Basingstoke and Deane Borough Council
- Appeal type
- other · Community Infrastructure Levy Appeal
- Procedure
- Written Representations
- Development
- other · Not Applicable
- Inspector
- McEntee K
Main issues, as the Inspector framed them
- Whether the appellant's failure to assume liability and failure to submit a Commencement Notice before commencing works constituted breaches of the CIL Regulations
- Whether the Council issued a Demand Notice with an incorrectly determined deemed commencement date
What decided it
A material operation in the form of a vehicle access had been carried out on the site, constituting commencement of the chargeable development, and liability was not assumed and no Commencement Notice was submitted before works began.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®