Planning appeal decision

Notice varied and upheld19 March 20243316909

29 Furnace Parade, TIPTON, DY4 9BB

without planning permission, the construction of a fence and gate to the front of the land over 1 metre in height and the construction of a fence to the rear of the land over 2 metres in height

Authority
Sandwell Metropolitan Borough Council
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
other · Householder developments
Inspector
Dudley G

Main issues, as the Inspector framed them

  • Whether the construction of fences and a gate constitutes a breach of planning control
  • Whether the steps required by the enforcement notice exceed what is necessary to remedy the breach
  • The appropriate period for compliance with the enforcement notice

What decided it

The fences exceed the heights permitted under permitted development rights and therefore constitute a breach of planning control that must be remedied, but a reasonable compliance period of three months rather than four weeks is appropriate.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.

In the app this decision sits on the map beside every other appeal around it, with the full reasoning summary, the letter held on file, and the case law it applies.