Planning appeal decision

Notice varied and upheld20 November 20233318085

91, 91A and 91B HIGH STREET, WEALDSTONE, LONDON, HA3 5DL

Without planning permission, the unauthorised construction of a side to rear dormer on the land (“Unauthorised Development”)

Authority
London Borough of Harrow
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
other · Other minor developments
Inspector
Satheesan R

Main issues, as the Inspector framed them

  • Whether the time period specified in the enforcement notice for compliance falls short of what should reasonably be allowed

What decided it

The Inspector's assessment that an 11-month compliance period was proportionate and reasonable to allow time for re-housing vulnerable occupiers and carrying out remedial works.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.

In the app this decision sits on the map beside every other appeal around it, with the full reasoning summary, the letter held on file, and the case law it applies.