Planning appeal decision
130 Cadogan Terrace, LONDON, E9 5HP
‘The erection of a timber structure to the south elevation of the premises shown in the approximate location outlined in blue on the attached site plan in Appendix 1’
- Authority
- London Borough of Tower Hamlets
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Minor retail and services
- Inspector
- Griffin E
Main issues, as the Inspector framed them
- Whether the steps required by the enforcement notice exceed what is necessary to remedy the breach of planning control (ground f)
- Whether the period for compliance with the enforcement notice is reasonable (ground g)
What decided it
The enforcement notice's requirement to remove the timber structure is necessary to remedy the breach of planning control, and the compliance period was appropriately extended from 3 to 4 months to account for the change of occupier.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®