Planning appeal decision
Swan Wharf Moorings, Unit 9 Swan Wharf Business Centre, Waterloo Road, UXBRIDGE, UB8 2RA
Without planning permission, the construction of:
- Authority
- London Borough of Hillingdon
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Other minor developments
- Inspector
- Watson S
Main issues, as the Inspector framed them
- Whether the matters alleged in the enforcement notice have occurred (ground b)
- Whether the matters constitute a breach of planning control (ground c)
- Whether enforcement action could be taken at the date the notice was issued (ground d)
- Whether the requirements of the notice are reasonable (ground f)
- Whether the compliance period is reasonable (ground g)
- Whether the notice was properly served (ground e)
What decided it
The jetty structure was demonstrated to be a licensed boat capable of independent movement rather than a fixed jetty structure, therefore not constituting operational development, while the polytunnel was substantially reconstructed within the enforcement period and required removal.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®