Allowed24 September 20243338483

Brogborough Landfill Site, Woburn Road, Lidlington, Bedfordshire, MK43 0NY

the installation of a solar PV park development and associated infrastructure

Authority
Central Bedfordshire
Appeal type
other · Planning Appeal
Procedure
Inquiry
Development
utilities-energy · Unknown
Inspector
Ware P

Main issues, as the Inspector framed them

  • The effect of the development on the landscape character of the area, including the consequences for the landfill restoration scheme.
  • The effect on the biodiversity of the site and the wider area, with particular regard to skylarks.

What decided it

The substantial weight attributed to the provision of renewable energy outweighed the very limited landscape harm and the biodiversity impacts, which were adequately mitigated through the Skylark Mitigation Strategy.

the substantial benefit of renewable energy generation, together with moderate benefits from the existing grid connection and ecological enhancements, outweighed the very limited harm to landscape character

Plan policies cited: EE1, EE2, EE3, EE5, SP2, CC1, CC2