Planning appeal decision

Notice upheld29 May 20253339203

The Retreat, Northfleet Green, GRAVESEND, DA13 9PN

described as without the benefit of planning permission the erection of a single-storey outbuilding and pavilion on the Land

Authority
Gravesham Borough Council
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
other · Householder developments
Inspector
White P

Main issues, as the Inspector framed them

  • Whether the period for compliance specified in the enforcement notice (3 months) falls short of what should reasonably be allowed

What decided it

The 3-month compliance period is reasonable given the dry weather conditions available in the following months and the nature of the demolition work required.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.