Planning appeal decision

Allowed28 May 20243341152

1 Duddage Farm Cottages, Twyning, TEWKESBURY, Gloucestershire, GL20 6DB

Authority
Tewkesbury Borough Council
Appeal type
other · Community Infrastructure Levy Appeal
Procedure
Written Representations
Development
other · Not Applicable
Inspector
Ghafoor A

Main issues, as the Inspector framed them

  • Whether the Council has correctly determined the deemed commencement date of the chargeable development under CIL Regulations 118
  • Whether the surcharge has been calculated incorrectly under CIL Regulations 117(1)(c)

What decided it

The Council's own evidence from complaints and building control records between January 2018 and November 2021 demonstrated that material operations had commenced well before the deemed date of 10 January 2024, supporting the appellant's claim of commencement around 14 January 2021.