Planning appeal decision
Flamingo Park Club, Sidcup-By-Pass Road, Chislehurst, BR7 6HL
Formation of 16x electric vehicle charging spaces, with associated 8x chargers, substation and switchboard, and canopies
- Authority
- London Borough of Bromley
- Appeal type
- minor · Planning Appeal
- Procedure
- Written Representations
- Development
- utilities-energy · Other minor developments
- Inspector
- Savage M
Main issues, as the Inspector framed them
- Whether the appeal scheme is inappropriate development in the Green Belt having regard to the National Planning Policy Framework (December 2024) and relevant development plan policies
- The effect of the appeal scheme on trees and the consequential effect on the character and appearance of the area
What decided it
The appeal site comprises previously developed land (Grey Belt) where the proposed development would not cause substantial harm to Green Belt openness and would meet a demonstrable need for renewable energy and EV charging infrastructure.
The benefits of providing renewable energy generation and meeting the demonstrable need for EV charging infrastructure in an area with little rapid charging provision outweighed any limited harm to Green Belt openness, particularly as the site comprises Grey Belt land that does not strongly contribute to Green Belt purposes.
Framework references: 110, 115, 143, 153, 154, 155
Plan policies cited: Policy G2 of the London Plan (2021), Policy 49 of the Bromley Local Plan 2019, Policy D4 of the London Plan, Policy G7 of the London Plan, Policy 37 of the Bromley Local Plan, Policy 73 of the Bromley Local Plan
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®