Planning appeal decision
Land North Of Manor Farm, Noke, OX3 9TU
Development of a ground mounted solar farm incorporating the installation of solar PV panels, associated infrastructure and access, as well as landscape planting and designated ecological enhancement areas
- Authority
- Cherwell District Council
- Appeal type
- major · Planning Appeal
- Procedure
- Written Representations
- Development
- utilities-energy · Major offices/R&D/light industry
- Inspector
- Gethin T
Main issues, as the Inspector framed them
- The effect of the proposed development on the character and appearance of the surrounding landscape
What decided it
The substantial and extensive environmental, social and economic benefits of the renewable energy development, particularly the generation of up to 26.6 megawatts of renewable energy and significant biodiversity net gain, were sufficient to outweigh the moderate landscape harm and conflict with development plan policies.
Framework references: 155
Plan policies cited: Policy ESD 14, Policy C28, Policy ESD 5, Policy ESD 13, Policy ESD 15, Policy ESD 10
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®