Notice upheld9 July 20253363275

2 Chapel Lane, Wilmslow, SK9 5HX

Without planning permission, the construction of a building”

Authority
Cheshire East
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
other · Householder developments
Inspector
McEntee K

Main issues, as the Inspector framed them

  • Whether the compliance period for the enforcement notice should be extended from 2 calendar months to 6 months

What decided it

The appellant had already been afforded nearly 6 months from submission of the appeal to the decision date to raise funds and find a contractor, which the Inspector considered a reasonable and proportionate compliance period.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.