Planning appeal decision
Notice upheld9 July 20253363275
2 Chapel Lane, Wilmslow, SK9 5HX
Without planning permission, the construction of a building”
- Authority
- Cheshire East
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Householder developments
- Inspector
- McEntee K
Main issues, as the Inspector framed them
- Whether the compliance period for the enforcement notice should be extended from 2 calendar months to 6 months
What decided it
The appellant had already been afforded nearly 6 months from submission of the appeal to the decision date to raise funds and find a contractor, which the Inspector considered a reasonable and proportionate compliance period.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®