Planning appeal decision
4-6 Brockenhurst Road & 11 Oliver Road, Ascot, SL5 9DL
Planning appeal 3377196 at 4-6 Brockenhurst Road & 11 Oliver Road, Ascot, SL5 9DL (Royal Borough of Windsor and Maidenhead) was dismissed on 19 May 2026 by Inspector Buchanan R, by written representations. The main issue, as the Inspector framed it: Whether the period for compliance with the enforcement notice is reasonable and proportionate.
Without planning permission, the removal of the roof and the construction of one additional storey”
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Other minor developments
- Inspector
- Buchanan R
- Postcode
- SL5 9DL
Main issues, as the Inspector framed them
- Whether the period for compliance with the enforcement notice is reasonable and proportionate
What decided it
The compliance period of approximately six months from the decision date, accounting for time already elapsed, was considered reasonable and proportionate for the appellant to undertake surveys, engage contractors, and complete the required works.
The decision letter
Town Planner Pro holds this letter. The Appeals plan opens it and every other letter we hold, all of them searchable, with the main issues and what decided each case picked out. We do not show letters on the free site because they carry people’s names and addresses.
With an account
What an account adds to this decision


More decisions in Royal Borough of Windsor and Maidenhead
The authority’s record since 2016 · every decision in 2026
- Notice upheld24 September 20263353235Sunnyside Stanwell Road, Horton, Slough, SL3 9PE
- Notice upheld24 September 20263353234Sunnyside Stanwell Road, Horton, Slough, SL3 9PE
- Notice varied and upheld17 September 202633621832 Aston Mead, Windsor, SL4 5PW
- Notice upheld10 August 20263369085Land to the Side of 16 Halfway Houses, Maidenhead Road, Maidenhead, Berkshire, SL6 6PP
- Notice upheld2 July 202633698378 Clare Road, Maidenhead, SL6 4DG
The main issues, what decided it, the planning balance and the policies and judgments listed as cited are read from the published letter by Town Planner Pro and are our summary, not the Inspector’s words; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®