Planning appeal decision
37 Harley Road, Cressage, SY5 6DF
permission in principle for the construction of one or two dwellings
- Authority
- Shropshire
- Appeal type
- minor · Planning
- Procedure
- Written
- Development
- residential
- Postcode
- SY5 6DF
Main issues, as the Inspector framed them
- Whether the site is suitable for residential development having regard to its location, the proposed land use and the amount of development with particular regard to the Council's strategy for the location of housing and its access to services and facilities
What decided it
The Council's inability to demonstrate a five-year housing land supply, combined with the site's sustainable location with access to services and public transport, means the presumption in favour of sustainable development applies and the benefits of housing delivery outweigh the conflict with the development plan's countryside control policies.
The adverse impacts of conflict with the development plan's countryside control policies, to which limited weight was attributed, do not significantly and demonstrably outweigh the benefits of housing delivery and modest economic benefits, when assessed against the Framework taken as a whole, triggering the presumption in favour of sustainable development under paragraph 11.
Framework references: 11
Plan policies cited: CS Policy CS1, CS Policy CS5, CS Policy CS6, SAMDev Policy MD1, SAMDev Policy MD7a, SAMDev Policy MD2
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®