Planning appeal decision

Allowed13 August 20266009830

Kensington Centre, 66 Hammersmith Road, London, W14 8UD

demolition of the existing building and the construction of a new building of up to 11 storeys in height (plus basement level and plant at roof level) comprising a self - storage facility (Use Class B8, up to 22,891sm GIA), affordable workspace (Use Class E(g)(i), 1162sm GIA) and community space (Use Class F2(b), 388sm GIA), together with an undercroft parking and servicing area accessed via a new vehicular crossover on Blythe Road, landscaping and associated works

Authority
London Borough of Hammersmith and Fulham
Appeal type
major · Planning
Procedure
Written
Development
employment-industrial
Postcode
W14 8UD

Main issues, as the Inspector framed them

  • Whether the submitted details are sufficient for the conditions to be discharged to ensure construction activities are managed and completed safely with minimal disruption to the occupiers of surrounding properties, with particular regard to highway safety for all users

What decided it

The submitted CLP provides sufficient detail and certainty to manage construction vehicle activity safely with appropriate mitigation measures, and there is no compelling site-specific evidence to justify additional detail beyond that provided in the guidance.

Plan policies cited: Policy T7 of the Hammersmith and Fulham Local Plan (2018)