Planning appeal decision
Mission House, Ledston Luck Villas, Kippax, LEEDS, LS25 7BU
Without planning permission the erection of three timber sheds in the curtilage of the dwelling house
- Authority
- Leeds City Council
- Appeal type
- enforcement · Enforcement Notice
- Procedure
- Written Representations
- Development
- other · Householder developments
- Inspector
- McEntee K
Main issues, as the Inspector framed them
- Whether the two-month compliance period for the enforcement notice is reasonable and proportionate
What decided it
The Inspector found that the appellant would have approximately 6 months in total to comply with the notice, which was a reasonable and proportionate period that provided an appropriate balance between the appellant's circumstances and the need to remedy the Green Belt harm.
The balance struck was between the appellant's personal circumstances and welfare concerns against the need to bring an end to the harm caused to the surrounding Green Belt by unauthorised development, with the balance tipping in favour of upholding the enforcement notice with the compliance period as originally set.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®