Planning appeal decision

Notice upheld16 December 20213281237

Mission House, Ledston Luck Villas, Kippax, LEEDS, LS25 7BU

Without planning permission the erection of three timber sheds in the curtilage of the dwelling house

Authority
Leeds City Council
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
other · Householder developments
Inspector
McEntee K

Main issues, as the Inspector framed them

  • Whether the two-month compliance period for the enforcement notice is reasonable and proportionate

What decided it

The Inspector found that the appellant would have approximately 6 months in total to comply with the notice, which was a reasonable and proportionate period that provided an appropriate balance between the appellant's circumstances and the need to remedy the Green Belt harm.

The balance struck was between the appellant's personal circumstances and welfare concerns against the need to bring an end to the harm caused to the surrounding Green Belt by unauthorised development, with the balance tipping in favour of upholding the enforcement notice with the compliance period as originally set.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.