Planning appeal decision

Allowed3 July 20253358116

Land At Grid Reference 230351 101882, Pyworthy, Devon, EX22 6LA

Stoneworthy Energy Storage System is a proposed battery energy storage system (BESS) comprising approximately 32no. battery enclosures, 16no. PCS (power conversion systems), 16no. MV skids (PCS transformer and switchgear), a 33kV substation building with a high voltage area containing auxiliary transformer and grid compliance equipment, a 132kV grid transformer with associated equipment and a grid connection to a National Grid Electricity Distribution (NGED) overhead line

Authority
Torridge District Council
Appeal type
major · Planning Appeal
Procedure
Written Representations
Development
utilities-energy · Other Major Developments
Inspector
Gethin T

Main issues, as the Inspector framed them

  • The effect of the proposed development on the character and appearance of the surrounding landscape, with particular regard to its countryside location

What decided it

The substantial economic, social and environmental benefits of the battery energy storage facility in supporting renewable energy supply, energy security, and achieving net zero carbon targets outweigh the localised and limited landscape harm and resulting conflict with the development plan.

Plan policies cited: Policy DM08A, Policy ST07

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.