Planning appeal decision
Carr Farm, Carr Lane, Tickton, BEVERLEY, East Riding Of Yorkshire, HU17 9SD
construction of 49.9MW solar farm comprising of ground mounted solar panels, underground cabling, a temporary construction compound, access tracks, perimeter fencing with CCTV cameras, access gates and associated ancillary grid infrastructure and work s
- Authority
- East Riding of Yorkshire Council
- Appeal type
- major · Planning Appeal
- Procedure
- Written Representations
- Development
- utilities-energy · Other Major Developments
- Inspector
- Hughes L
Main issues, as the Inspector framed them
- The effect of the proposed development on the character and appearance of the area, with particular regard to cumulative impact
What decided it
The significant contribution to mitigating climate change and achieving net zero ambitions, combined with local economic benefits and substantial biodiversity net gain, outweighed the moderate harm to character and appearance and development plan conflict.
Framework references: 11, 57, 161, 187, 212, 215
Plan policies cited: Policy S4, Policy EC5, Policy ENV1, Policy ENV3
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®