Planning appeal decision

Notice upheld3 July 20253362267

Land at 1 Creskeld Garth, Bramhope, Leeds, LS16 9EW

Without planning permission the erection of gate piers and sliding gates to existing driveway exceeding one metre in height adjacent to a highway used by vehicular traffic”

Authority
Leeds City Council
Appeal type
enforcement · Enforcement Notice
Procedure
Written Representations
Development
other · Householder developments
Inspector
McEntee K

Main issues, as the Inspector framed them

  • Whether the compliance period for the enforcement notice should be extended to 12 months to allow time for pre-application consultation and submission of alternative planning proposals

What decided it

The Inspector has no power under ground (g) to extend the compliance period as this would amount to granting temporary planning permission, and the time already available (nearly seven months from decision date) is reasonable and proportionate for the appellant to pursue alternative proposals and comply with the notice.

The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.