Planning appeal decision
Dismissed25 March 20243323848
R/O 39 St Aubyns, Hove, East sussex, BN3 2TH
- Authority
- Brighton and Hove City Council
- Appeal type
- ldc · Lawful Development Certificate
- Procedure
- Written Representations
- Development
- community-institutional · Change of use
- Inspector
- Symons G
Main issues, as the Inspector framed them
- Whether the Council's decision was well founded
What decided it
The documentary evidence only extends to 2014, falling well short of the ten-year requirement, and the use was too intermittent and limited in frequency to constitute a substantially uninterrupted material change of use.
The main issues and the deciding factor are read from the published letter by Town Planner Pro; the letter itself is the record. Contains public sector information licensed under the Open Government Licence v3.0. Research, not advice.
®